is seeking certified and qualified DBE and DVBE subcontractors and/or suppliers to provide Underground utilities, earthwork, concrete, metal fabrications, mechanical, and electrical
Water Treatment Plant Generator Improvement Project at Facility 98
100126
City of San Luis Obispo
1900 Stenner Creek Rd., San Luis Obispo, CA, 93405
09-29-2022 at 02:00 PM
Brad Edwards
805-335-1161
805-614-9909
PO Box 350, Nipomo, CA, 93444
PROJECT DETAILS:
The project includes construction of a new 1250kW, 480Y/277V diesel engine driven generator, 2500 gallon fuel tank, 2000A Bus Main Switchboard, Automatic Transfer Switch, and site improvements at the City of San Luis Obispo Water Treatment Plant.
All work to be completed to industry standards and best practices. Further details available in specs.
Plans are available electronically from be@edwardscongroup.com. All bids and material quotes must be per plans and specifications. All bids are required to be received in our office through our e-mail or fax number at least 1-2 business days before Bid Due Date so that we have ample time to fill out the required bid forms for the owner. Edwards Construction Group, Inc. is an Equal Opportunity Employer. Bonds may be required and subcontractor must agree to our subcontract agreement.